Date: April 2020 – June 2020 Client: SEPA Location: Toorak Rd Level Crossing Subcontract Value: $2,100,000
Overview
As part of the South East Program Alliance, Gearon Civil were engaged to complete the removal of the redundant level crossing at Toorak Road. Works were completed during full road shutdowns shift working with alternating crews. The adjacent Talbot Crescent was also upgraded to intersect with Toorak Rd.
Scope of Works
Earthworks including demolition of existing road infrastructure
Stormwater and Subsurface Drainage
Subgrade Improvement
Pavement Construction
Deep lift asphalt and wearing course
Line marking
Concrete Kerb
Bluestone Kerb
Tactiles
Signage
Executive Summary
Gearon Civil was pleased to deliver another rail crossing road work project successfully. The Toorak Rd LXRP provided the normal challenges of a large-scale rail occupation project with the co-ordination of many trades and work front interfaces.
It was delivered in a productive 24/7 program, through Easter, with excellent safety and quality outcomes and with the full the satisfaction of the client.