Date: May 2017- July 2021 Client: Icon Constructions Location: Camp Road Broadmeadows Subcontract Value: $16,000,000
Overview
Extensive siteworks for building benches, roadworks and carparks to enable the construction and development of a new production facility at the CSL plant in Broadmeadows.
Details
Bulk Earthworks including excavation in rock (120,000m3)
Stormwater Drainage
HV electric conduit installation (8km)
Construction of Wetlands (18,000m3)
HD pavement construction and associated works (20,000m2)
Retaining walls
Piling
Executive Summary
Gearon Civil was pleased to help Icon Constructions deliver this significant project for CSL and Melbourne.
The project provided the normal challenges of a large-scale building project with the co-ordination of many trades and moving targets. The project was delivered in a productive and collaborative environment with excellent safely and quality outcomes and with the full the satisfaction of the client.